The installation method of single-pipe rigid support and hanger involves several key steps and precautions to ensure the effectiveness and safety of the support and hanger. The following are some of the main installation requirements and methods:
Adjusting and fixing the hanger: The hanger should have a vertical adjustment facility to adjust the pipe to the predetermined elevation, and use a gauge or force wrench to confirm that the hanger is under load. After the pipe elevation adjustment is completed, it should be locked to prevent the hanger rod from rotating and loosening. The hanger should be able to swing freely with the horizontal displacement of the pipe, unless it is a small-diameter, light-loaded and vibration-free pipe hanger. The hanger rod is allowed to be directly fixed in the concrete member.
Connection with the building structure: When the hanger is directly suspended on the steel beam with a steel beam, the clamp's fastening device should be tightened to ensure that the clamp is fixed to the steel beam. For a specific model of C-beam clamp, the screw tightening torque should comply with the provisions of the design documents. Direct welding or screw connection with building steel structure should comply with the requirements of GBJ17GBJ 205. It is strictly forbidden to cut holes in steel structure. Drilling holes in building steel structure must be approved by relevant designers in advance.
Welding and bearing: Welding with concrete parts should strive to shorten the welding time. Intermittent welding can be used when necessary to avoid high welding temperature affecting concrete strength. Welding with alloy steel pipes should be carried out in the factory. If welding is necessary on site, the preheating before welding and post-welding heat treatment system should be strictly implemented. The bearing surface of each bearing plate welded on the pipeline should be in the same plane perpendicular to the pipeline axis. The pipe clamp must be installed close to all bearing ribs to ensure that the bearing ribs are evenly loaded.
Seismic design: According to GB50981-2014 Code for seismic design of building mechanical and electrical engineering, each section of horizontal straight pipeline should be equipped with lateral seismic support and hanger at both ends. When the distance between two lateral seismic supports and hangers is greater than the maximum design distance, a lateral seismic support and hanger should be added in the middle. Each section of horizontal straight pipe should be equipped with at least one longitudinal seismic support and hanger. When the distance between two longitudinal seismic supports and hangers is greater than the maximum design distance, longitudinal seismic supports and hangers should be added in sequence according to the spacing specified in this specification. The distance between the diagonal brace and the hanger of the seismic support and hanger shall not be greater than 0.1m.
Other precautions: The installation of the bracket should be carried out simultaneously with the installation of the pipeline. After the installation of the support and hanger is completed, the bracket should be wiped clean, and all exposed channel steel ends should be covered. The movable parts of all movable brackets should be exposed and should not be covered by insulation. For pipelines with thermal displacement, when they expand due to heat, the support and hanger should be checked and adjusted in time.
These steps and precautions together constitute the basic framework for the installation of single-tube rigid supports and hangers, ensuring the stability and safety of the supports and hangers, while also taking into account the necessity of earthquake-resistant design to improve the safety and durability of building mechanical and electrical engineering.